PODIUM LEVEL 1 POUR 1 SUSPENDED SLAB | BASEMENT 2 POUR 7 SUSPENDED SLAB

On Wednesday the 11th of October (weather permitting, or the following business day) the above project will require its hours of operation to be extended in order to enable the successful completion of the Level 1 Pour 1 & Basement 2 Pour 7 Critical Concrete Pours.

Setup works will commence from 7:00 am and aim to be completed by 9:30 pm. Our staff will be present during these works to ensure noise is kept at a minimum.

Notification has been provided to the council and rangers.  

We are more than happy to respond to any queries you have and look forward to completing these works as soon as possible with your co-operation.

Registering your details at the below email will assist us in maintaining regular contact before, during and at the completion of works email: info@nspconstruction.com.au.